The purpose of this project was to abandon an old 4” water main and interconnect existing 6” mains in the area to improve service and fire protection.
The project was expected to last approximately 4 months at an approximate cost of $300,000. Due to some delays in construction, street repair and other site restoration was not able to be completed before the arrival of winter. These items will be finished in the spring of 2011.